Which two elements are used to assess risk in OSB mission planning?

Study for the RAAF Officer Selection Board Test. Prepare with tailored quizzes and insights on key areas, featuring detailed hints and explanations. Excel in your RAAF OSB exam!

Multiple Choice

Which two elements are used to assess risk in OSB mission planning?

Explanation:
Assessing risk in mission planning relies on two factors: how likely something is to occur and how severe the outcome would be. This likelihood–consequence approach forms the basis of a risk rating, guiding decisions on whether to accept, mitigate, or avoid a risk. Weather or terrain can influence those factors but are not the pair used to define risk itself, and cost, schedule, or command hierarchy relate to other aspects of planning rather than the risk measurement framework. So, the two elements used to assess risk are likelihood and consequence.

Assessing risk in mission planning relies on two factors: how likely something is to occur and how severe the outcome would be. This likelihood–consequence approach forms the basis of a risk rating, guiding decisions on whether to accept, mitigate, or avoid a risk. Weather or terrain can influence those factors but are not the pair used to define risk itself, and cost, schedule, or command hierarchy relate to other aspects of planning rather than the risk measurement framework. So, the two elements used to assess risk are likelihood and consequence.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy